1
|
Change of Land Use
|
Department of Housing and Urban Development
|
40 days
|
|
Department of Local Government
|
40 days
|
|
2
|
Approval of layout Plan
|
Department of Housing and Urban Development
|
40 days
|
|
Department of Local Government
|
40 days
|
|
3
|
Approval of Building Plan
|
Chief Town Planner, Department of Housing and Urban Development
|
40 days
|
|
Department
of Local Government
|
40 days
|
|
PUDA
|
40 days
|
|
Director of Factories
|
40 days
|
|
PSIEC
|
40 days
|
|
4
|
Sanction of Water Supply and Sewerage Connection
|
PSIEC
|
10 days
|
|
Department of Local Government /Municipal Corporation/Council
|
10 days
|
|
PUDA
|
10 days
|
|
5
|
Consent to Establish(NOC)
|
Punjab Pollution Control Board
|
Green Category
|
15 days |
|
Large & Medium
|
21 days |
|
Small Scale |
15 days
|
|
CSA-cum-SAC
|
21 days
|
|
6
|
Consent to Operate
|
Punjab Pollution Control Board
|
Green Category
|
15 days |
|
Large & Medium |
30 days |
|
7
|
Sanction/Release of Power Connection
|
Punjab State Electricity Board
|
|
Issue of demand notice: |
|
|
|
|
L.T. Supply (upto 650 V) |
w.e.f. date of registration of application |
7 days |
|
|
HT/EHT Supply (above 650 V) |
w.e.f. from the date of receipt of application |
10 days |
|
Release of Power Connection: |
|
|
|
|
Without augmentation/ erection / extension of system |
|
30 days |
|
|
Where only augmentation is involved |
LT Supply |
45 days |
|
HT Supply |
60 days |
|
EHT Supply |
120 days |
|
|
Where erection of system is involved |
Regulator will decide the time period |
|
|
Above time periods will be subject to change as per the Electricity Supply Code
as approved by the Regulatory Commission from time to time |
|
30 days |
|
Chief Electrical Inspector
|
21 days
|
|
8
|
Permission to Install Generator Set
|
PSEB
|
30 days
|
|
Chief Electrical Inspector
|
30 days
|
|
9
|
Grant of License for Factory
|
Director of Factories
|
15 days
|
|
10
|
Approval for Use of Forest Land
|
Chief Conservator of Punjab
|
Where no forest land is involved
|
15 days
|
|
Processing & Referring time of application to Govt. of India for approval |
45 days |
|
11
|
Registration under VAT
|
Department of Excise & taxation
|
30 days
|
|
Note: All timelines start from receipt of complete application by the Competent Authority.
|
|